Hazel Finch Labs is a proud supporter of The Maine Monitor.

News This is a news story based on facts, either observed and verified firsthand by the reporter, or reported and verified from knowledgeable sources.

Voters to decide Nov. 3 on raising Lubec Water District debt limit from $200,000 to $2 million

Approval would allow the utility to accept $720,000 in state loan funds for a multiyear pipe replacement project.
a sign on the side of a building that reads greetings from lubec, maine
Photo by Stephanie McFeeters.

LUBEC — Local voters face a Nov. 3 referendum on whether to raise the Lubec Water District’s debt limit from $200,000 to $2 million to fund critical infrastructure upgrades.

Laurie Tinker, the district’s office manager, addressed the Board of Selectmen on Wednesday night to explain the urgent need for debt relief, emphasizing that the district does not plan to spend the full $2 million.

“Our district board has no intention of spending $2 million,” Tinker said.

State lawmakers capped the district’s borrowing at $200,000 in 1951 — an amount equivalent to more than $2.6 million today.

Working with Winterport civil and environmental engineering firm Olver Associates Inc., the district secured a $720,000 package from the state’s Drinking Water State Revolving Loan Fund this year. However, the debt cap prevents the district from accepting the funds. Tinker said the district must accept the money by April 22.

The funding, which includes a loan with $150,000 in principal forgiveness, is expected to cover the design phase of a project to replace North Lubec’s water pipes. Crews laid the original pipes in 1901, Water District Superintendent Mike Morey told the Board of Selectmen.

The project to replace the aging waterlines spans three years and carries an estimated $7 million price tag, Tinker said. The district has secured $2 million through efforts led by U.S. Sens. Angus King and Susan Collins, with additional support expected from the Maine Drinking Water Program and the U.S. Department of Agriculture.

Tinker, who joined the district in 2021 as office manager and bookkeeper, told Monitor Local in a telephone interview that the utility has been fortunate to maintain operations under the $200,000 cap this long. She noted that the district likely exceeded the debt limit during water tower construction in the 1980s.

Beyond delaying the North Lubec project, the 1951 borrowing limit leaves the district unprepared for emergency repairs, as $200,000 provides little purchasing power today, Tinker said.

Operating costs have skyrocketed for basic supplies and power, Tinker noted. Fire hydrants that once cost $800 now sell for $3,000, while electricity expenses to run water pumps and pipe heating systems have doubled since the COVID-19 pandemic.

To keep pace with rising operational expenses, the district increased customer rates 4 percent in 2025 and an additional 40 percent in September following six years of unchanged rates.

Town Administrator Suzette Francis said the town office has already received about 200 absentee ballots for the Nov. 3 local vote.

Failing to pass the referendum would force the district to seek state legislative action to adjust the cap, likely missing the state funding deadline.

The Lubec Water District board of trustees’ next meeting, which is open to the public, is scheduled for Nov. 5.


WERU Community Radio is a proud supporter of The Maine Monitor.
Share
headshot of the reporter

Ethan Bien

Ethan Bien is a writer and documentary filmmaker based in Lubec. He reports on downeast Maine for Monitor Local, an initiative of The Maine Monitor.

Contact Ethan via email with questions, concerns or story ideas:



Don't Miss These Stories

Total
0